Economy, Banking and Finance · 11 March 2026

Ministry of Power (MoP) targets 143 GW inter-regional transmission capacity by 2027

Exam-focused facts from the 11 March 2026 current affairs briefing.

Key facts

  • Union Minister of State for Power Shripad Naik informed the Rajya Sabha that India's inter-regional transmission capacity is set to reach 143 GW by 2027 and 168 GW by 2032.
  • The inter-regional transmission capacity of the National Grid stood at 120 GW as of December 2025.
  • The expansion of the National Grid is aimed at meeting a projected peak electricity demand of 388 GW by 2032.
  • Under the National Electricity Plan (NEP) Volume II Transmission, the transmission network of 220 kV and above is planned to expand to 6.48 lakh ckm by 2032.
  • The transformation capacity is projected to increase to 2,345 Giga Volt Ampere (GVA) by 2032.
  • Right-of-Way (RoW) issues have impacted the project timelines of 25 Inter-State Transmission System (ISTS) projects.