Government Schemes and Policy · 18 July 2026
Cabinet Approves 10 GWh ACC Battery Manufacturing Under PLI ACC Scheme
Exam-focused facts from the 18 July 2026 current affairs briefing.
Key facts
- The Ministry of Heavy Industries invited global bids for setting up 10 GWh cumulative capacity Advanced Chemistry Cell manufacturing facilities under the PLI ACC Scheme.
- Under the PLI ACC Scheme, out of the targeted 50 GWh capacity, 40 GWh has already been awarded to domestic manufacturers.
- The total budgetary outlay for the PLI Scheme on 'National Programme on Advanced Chemistry Cell Battery Storage' is ₹18,100 crore.
- The 10 GWh capacity is earmarked for Grid Scale Stationary Storage application to support energy storage requirements from renewable energy deployment.